What does 'Completed' status on a machine after a scheduled patching run?

After a patch schedule has been executed and a machine shows a Current Phase that it is 'Completed'; what does this mean?

It means that the scheduled patching run has finished, it doesn't give any status of any failed patches. To identify if there are any issues with the scheduled patching run for specific machines, you can find that information here:

1. Patching Report to display a list of failed active patches for each client machine.

2. Machine inventory -> Security -> Patching Detect/Deploy Status -> Deployment Status -> All to list out all the patches

3. Patch listing -> Specific patch -> Drill into the patch -> Deployment status -> to see all machines deployed to

Please note in future releases of the K1000 appliance updates, there will be more descriptive information displayed to relay the Currrent Phase 'Complete' status.

attached files: CompleteStatus.PNG